Projects

From data centers and industrial complexes to major GDOT highway widenings, our portfolio proves that we deliver more than just asphalt—we deliver schedule certainty. For nearly 50 years, Baldwin Paving has leveraged vertical integration and financial strength to execute complex projects across Metro Atlanta and throughout Georgia, ensuring every job is completed on time, within budget, and built to last.

Completed Projects

See the scale and quality of our work firsthand. From major highways to commercial developments, these projects reflect our commitment to excellence.

Commercial Paving
Heavy Civil

CHOA Arthur Blank Hospital, Druid Hills Rd. NE

2220 North Druid Hills Rd NE, Atlanta, 30329

This project involved milling and widening along Briarcliff Road and Tullie Circle, followed by full‑depth of the interior asphalt pavement sections and the hospital’s ring road. Baldwin maintained an accelerated construction schedule while ensuring uninterrupted emergency access and continuous hospital traffic flow throughout all paving operations. A total of more than 24,000 tons of combined asphalt materials were placed. Subcontracted scopes included temporary traffic control, curb and gutter installation, pavement striping, and regulatory and guide signage.

View Project

CHOA Arthur Blank Hospital, Druid Hills Rd. NE

2220 North Druid Hills Rd NE, Atlanta, 30329

This project involved milling and widening along Briarcliff Road and Tullie Circle, followed by full‑depth of the interior asphalt pavement sections and the hospital’s ring road. Baldwin maintained an accelerated construction schedule while ensuring uninterrupted emergency access and continuous hospital traffic flow throughout all paving operations. A total of more than 24,000 tons of combined asphalt materials were placed. Subcontracted scopes included temporary traffic control, curb and gutter installation, pavement striping, and regulatory and guide signage.

Costco, Fort Oglethorpe, Ringold

100 Cobb Pkwy, Ringold, GA 30736

This project involved the construction of both light duty and heavy duty asphalt pavement built to rigorous specifications. The team delivered the work ahead of schedule while meeting all project requirements. Baldwin oversaw the GAB installation, milling of all joints, and execution of the asphalt paving operations. Subcontractors supported the project by providing traffic control, pavement striping, and signage installation.Throughout the project, comprehensive safety measures were enforced, including detailed traffic control plans, daily jobsite safety briefings, strict equipment and truck movement protocols, PPE compliance, and continuous coordination to meet Costco’s safety standards.

View Project

Costco, Fort Oglethorpe, Ringold

100 Cobb Pkwy, Ringold, GA 30736

This project involved the construction of both light duty and heavy duty asphalt pavement built to rigorous specifications. The team delivered the work ahead of schedule while meeting all project requirements. Baldwin oversaw the GAB installation, milling of all joints, and execution of the asphalt paving operations. Subcontractors supported the project by providing traffic control, pavement striping, and signage installation.Throughout the project, comprehensive safety measures were enforced, including detailed traffic control plans, daily jobsite safety briefings, strict equipment and truck movement protocols, PPE compliance, and continuous coordination to meet Costco’s safety standards.

Kroger Distribution Center, Fort Gillem

2000 Anvil Block Road in Forest Park, GA

This project includes a state-of-the-art distribution center on the nearly 1,000-acre Fort Gillem property, a former U.S. Army base, in Forest Park, Ga. The 1 million-square-foot distribution center services existing operations in Alabama, Georgia, South Carolina and Tennessee. Baldwin Paving completed 101,000 tons of asphalt paving in 3 months on this project. It included strong coordination between our project manager, multiple crews on the project simultaneously, quality control/assurance, plant operations, and our safety team.‍

View Project

Kroger Distribution Center, Fort Gillem

2000 Anvil Block Road in Forest Park, GA

This project includes a state-of-the-art distribution center on the nearly 1,000-acre Fort Gillem property, a former U.S. Army base, in Forest Park, Ga. The 1 million-square-foot distribution center services existing operations in Alabama, Georgia, South Carolina and Tennessee. Baldwin Paving completed 101,000 tons of asphalt paving in 3 months on this project. It included strong coordination between our project manager, multiple crews on the project simultaneously, quality control/assurance, plant operations, and our safety team.

Amazon Stonewall, Tell Rd., Union City

5115 Stonewall Tell Rd Union City GA 30349

This project consisted of GAB placement, asphalt paving, and curb and gutter installation. Baldwin performed the fine grading, asphalt milling, and all asphalt paving operations, successfully installing over 20,000 tons of material on schedule. The project was completed over a 3 month timeline, meeting all production and delivery milestones. Our subcontractors handled traffic control, pavement striping, and ground‑post‑mounted signage installation.

View Project

Amazon Stonewall, Tell Rd., Union City

5115 Stonewall Tell Rd Union City GA 30349

This project consisted of GAB placement, asphalt paving, and curb and gutter installation. Baldwin performed the fine grading, asphalt milling, and all asphalt paving operations, successfully installing over 20,000 tons of material on schedule. The project was completed over a 3 month timeline, meeting all production and delivery milestones. Our subcontractors handled traffic control, pavement striping, and ground‑post‑mounted signage installation.

Great Wolf Lodge

150 Tom Hall Parkway LaGrange GA 30240
View Project

Great Wolf Lodge

150 Tom Hall Parkway LaGrange GA 30240

Coscto Athens

5550 Parkway Blvd, Athens GA 30606
View Project

Coscto Athens

5550 Parkway Blvd, Athens GA 30606

Macon Spec Building

439 Mulberry ST, Macon, GA 31021

This project involved the construction of both light duty and heavy duty asphalt pavement sections. Baldwin executed the complete installation scope, including soil cement stabilization, graded aggregate base (GAB) placement, and full asphalt paving operations using established compaction and quality control procedures. Subcontracted partners provided traffic control services, applied pavement striping in accordance with project specifications, and installed all required signage components.

View Project

Macon Spec Building

439 Mulberry ST, Macon, GA 31021

This project involved the construction of both light duty and heavy duty asphalt pavement sections. Baldwin executed the complete installation scope, including soil cement stabilization, graded aggregate base (GAB) placement, and full asphalt paving operations using established compaction and quality control procedures. Subcontracted partners provided traffic control services, applied pavement striping in accordance with project specifications, and installed all required signage components.

I-75 Resurfacing

I-75

This project consists of replacing the pavement that was in poor overall condition along I-75 from Beltline Trail to just south of the bridge over the I-75 ramp to I-85 in Fulton County. GDOT proposed to resurface the 12.5mm Poly and OGFC on I-75 for a distance of 5.96 miles. The project also consisted of repaving the shoulders and ramps, and replacing thermo and loops. Baldwin Paving is responsible for manufacturing and placing 55,000 Tons of Asphalt, 191,000 SY of milling, and Traffic Control. Our Subcontractors are responsible for micro milling, installation of thermo, and installation of loops.

View Project

I-75 Resurfacing

I-75

This project consists of replacing the pavement that was in poor overall condition along I-75 from Beltline Trail to just south of the bridge over the I-75 ramp to I-85 in Fulton County. GDOT proposed to resurface the 12.5mm Poly and OGFC on I-75 for a distance of 5.96 miles. The project also consisted of repaving the shoulders and ramps, and replacing thermo and loops. Baldwin Paving is responsible for manufacturing and placing 55,000 Tons of Asphalt, 191,000 SY of milling, and Traffic Control. Our Subcontractors are responsible for micro milling, installation of thermo, and installation of loops.

I-285 @ SR 400 Transform Improvement Project

Turner McDonald Parkway, Sandy Springs, GA 30346

This priority project adds new flyover ramps, new collector-distributor lanes and other facilities to aid east-west travel along I-285 and north-south travel along SR 400. This project consisted of 4.3 miles of I-285 from west of Roswell Road to east of Ashford Dunwoody Road and 6.2 miles along SR 400 from the Glenridge Connector to Spalding Drive. Baldwin Paving was responsible for Resurfacing nearly 400,000 tons, over 500,000 SYs of Milling, over 10,000 feet of storm drain, among other items like traffic control, soil cement, barrier wall, and stabilization to name a few. Baldwin was a critical stakeholder in completion of this project.

View Project

I-285 @ SR 400 Transform Improvement Project

Turner McDonald Parkway, Sandy Springs, GA 30346

This priority project adds new flyover ramps, new collector-distributor lanes and other facilities to aid east-west travel along I-285 and north-south travel along SR 400. This project consisted of 4.3 miles of I-285 from west of Roswell Road to east of Ashford Dunwoody Road and 6.2 miles along SR 400 from the Glenridge Connector to Spalding Drive. Baldwin Paving was responsible for Resurfacing nearly 400,000 tons, over 500,000 SYs of Milling, over 10,000 feet of storm drain, among other items like traffic control, soil cement, barrier wall, and stabilization to name a few. Baldwin was a critical stakeholder in completion of this project.

Lambert High School

805 Nichold Rd, Suwanee GA 30024
View Project

Lambert High School

805 Nichold Rd, Suwanee GA 30024

Idlewood Elementary

1484 Idlewood Rd, Tucker GA 30084
View Project

Idlewood Elementary

1484 Idlewood Rd, Tucker GA 30084

Cherokee Co Middle School "C"

1555 Owens Store Rd Canton, GA 30115
View Project

Cherokee Co Middle School "C"

1555 Owens Store Rd Canton, GA 30115

East Coweta High School

400 Hwy 154 Sharpsburg GA 30277
View Project

East Coweta High School

400 Hwy 154 Sharpsburg GA 30277

Wellstar Paulding Hospital

600 W Memorial Dr Dallas GA 30132
View Project

Wellstar Paulding Hospital

600 W Memorial Dr Dallas GA 30132

Newnan Crossing Townhomes

151 Parkway North Newnan, GA 30265
View Project

Newnan Crossing Townhomes

151 Parkway North Newnan, GA 30265

Westfield Village Centex - Covington

3900 Salem Rd Covington GA 30016
View Project

Westfield Village Centex - Covington

3900 Salem Rd Covington GA 30016

Oak Grove At Jonesboro

1310 Jonesboro Rd McDonough, GA 30253
View Project

Oak Grove At Jonesboro

1310 Jonesboro Rd McDonough, GA 30253

Everhour

326 Green Top Rd Newnan Ga 30263

Woodberry Canton

Woodberry Ct Canton GA 30115
View Project

Woodberry Canton

Woodberry Ct Canton GA 30115

Prose McDonough

100 Oakbrook Dr McDonough GA 30253
View Project

Prose McDonough

100 Oakbrook Dr McDonough GA 30253

Lower Roswell Road

Lower Roswell Road Southeast, Cobb County, GA 30068

SR3 (Northside Dr) Beginning at Martin Luther King Jr Dr and extending to Rhodes St

35 Northside Drive Northwest, Atlanta, GA 30314
View Project

SR3 (Northside Dr) Beginning at Martin Luther King Jr Dr and extending to Rhodes St

35 Northside Drive Northwest, Atlanta, GA 30314

Woodstock Hub

Woodstock, GA 30146
View Project

Woodstock Hub

Woodstock, GA 30146

Riverside Dr Roundabout

Riverside Drive Northwest, Sandy Springs, GA 30328
View Project

Riverside Dr Roundabout

Riverside Drive Northwest, Sandy Springs, GA 30328

I-285 Reconstruction and Rehabilitation Project

2080 Pine Cone Drive Southwest, Atlanta, GA 30331

This project replaced the pavement that was in poor overall condition along I-285 west side from CS 843/Collier Drive to CR 2838/Paces Ferry Road in Fulton and Cobb Counties. GDOT proposed to replace the existing JPCP on I-285 a distance of 7.22 miles. The project also replaced the shoulders, concrete median barrier, glare screen and guardrail and corrected the existing substandard cross slope. Baldwin Paving is responsible for manufactoring and placing nearly 420,000 tons of asphalt, micromilling, and traffic control.

View Project

I-285 Reconstruction and Rehabilitation Project

2080 Pine Cone Drive Southwest, Atlanta, GA 30331

This project replaced the pavement that was in poor overall condition along I-285 west side from CS 843/Collier Drive to CR 2838/Paces Ferry Road in Fulton and Cobb Counties. GDOT proposed to replace the existing JPCP on I-285 a distance of 7.22 miles. The project also replaced the shoulders, concrete median barrier, glare screen and guardrail and corrected the existing substandard cross slope. Baldwin Paving is responsible for manufactoring and placing nearly 420,000 tons of asphalt, micromilling, and traffic control.

SR360/Macland Road, Widening & Reconstruction

Andrew Young International Boulevard Northeast, Atlanta, GA 30303

This project consisted of reconstructing SR 360 from a two-lane highway to a four-lane, median divided highway in Cobb and Paulding counties. The project was a 6.2 mile long stretch evenly split between Paulding county and Cobb county.

View Project

SR360/Macland Road, Widening & Reconstruction

Andrew Young International Boulevard Northeast, Atlanta, GA 30303

This project consisted of reconstructing SR 360 from a two-lane highway to a four-lane, median divided highway in Cobb and Paulding counties. The project was a 6.2 mile long stretch evenly split between Paulding county and Cobb county.

SR400 Resurfacing

Dawson County, Georgia

This project consisted of replacing the pavement that was in poor overall condition along SR400 in Dawson and Lumpkin Counties. GDOT proposed to resurface the 12.5mm Poly and OGFC on SR400 for a distance of 7.95 miles. The project also consisted of repaving the shoulders and ramps, as well as replacing thermo and loops. Baldwin Paving is responsible for manufacturing and placing 40,000 Tons of Asphalt, 380,000 SY of milling, and Traffic Control. Our Subcontractors are responsible for installation of thermo and installation of loops.

View Project

SR400 Resurfacing

Dawson County, Georgia

This project consisted of replacing the pavement that was in poor overall condition along SR400 in Dawson and Lumpkin Counties. GDOT proposed to resurface the 12.5mm Poly and OGFC on SR400 for a distance of 7.95 miles. The project also consisted of repaving the shoulders and ramps, as well as replacing thermo and loops. Baldwin Paving is responsible for manufacturing and placing 40,000 Tons of Asphalt, 380,000 SY of milling, and Traffic Control. Our Subcontractors are responsible for installation of thermo and installation of loops.

Pickens County Terminal Building Sitework

193 Pickens Airport Rd, Jasper, GA 30143

This project consisted of grading out and building a new parking lot for the new Pickens County Airport Terminal building. Baldwin was responsible for installing new 18" Storm Drain Pipe and drainage structures, moving dirt to build the new parking lot pad, placing GAB, installing new curb and sidewalk, and paving the new parking lot. Our subcontractors were responsible for erosion control, striping the parking lot, and installing new decorative fencing and gates around the parking lot.

View Project

Pickens County Terminal Building Sitework

193 Pickens Airport Rd, Jasper, GA 30143

This project consisted of grading out and building a new parking lot for the new Pickens County Airport Terminal building. Baldwin was responsible for installing new 18" Storm Drain Pipe and drainage structures, moving dirt to build the new parking lot pad, placing GAB, installing new curb and sidewalk, and paving the new parking lot. Our subcontractors were responsible for erosion control, striping the parking lot, and installing new decorative fencing and gates around the parking lot.

Construction of a Roundabout on SR14 at SR41

GA 14, Moreland, Coweta County, GA 30259

This project consisted of building a roundabout on SR 14 at SR 41. Baldwin was responsible for grading, placing GAB, installing 18" Storm Drain pipe, milling asphalt and paving asphalt. Our subcontractors were responsible for erosion control, installing all the curb and gutter, all the concrete flatwork, lighting poles and luminaires, drainage structures, striping and ground post-mounted signs.

View Project

Construction of a Roundabout on SR14 at SR41

GA 14, Moreland, Coweta County, GA 30259

This project consisted of building a roundabout on SR 14 at SR 41. Baldwin was responsible for grading, placing GAB, installing 18" Storm Drain pipe, milling asphalt and paving asphalt. Our subcontractors were responsible for erosion control, installing all the curb and gutter, all the concrete flatwork, lighting poles and luminaires, drainage structures, striping and ground post-mounted signs.

County Line, Auburn, Road Bridge Replacement

450 County Line Auburn Road, Barrow County, GA 30680

This project was designed to remove a historical rock culvert and replace with a new precast single barrel culvert. Baldwin was responsible for grading, placing GAB, building and pouring the footer foundation, placing and setting the precast culvert pieces, and paving asphalt. Our subcontractors were responsible for erosion control, guardrail, striping and ground post-mounted signs.

View Project

County Line, Auburn, Road Bridge Replacement

450 County Line Auburn Road, Barrow County, GA 30680

This project was designed to remove a historical rock culvert and replace with a new precast single barrel culvert. Baldwin was responsible for grading, placing GAB, building and pouring the footer foundation, placing and setting the precast culvert pieces, and paving asphalt. Our subcontractors were responsible for erosion control, guardrail, striping and ground post-mounted signs.

378 Mile of Widening for Turn Lanes on SR101 (Rockmart Road) at Old Draketown Trail

1 Old Draketown Trail, Carroll County, GA 30180

This project consisted of widening of a turn lane on SR 101 at Old Draketown Trail. Baldwin was responsible for grading, installing 18" Storm Drain pipe, drainage structures, GAB, milling asphalt, 18" Side Drain pipe (for driveways), paving asphalt. Our subcontractors were responsible for erosion control, striping, ground post mounted signs, and field fencing.

View Project

378 Mile of Widening for Turn Lanes on SR101 (Rockmart Road) at Old Draketown Trail

1 Old Draketown Trail, Carroll County, GA 30180

This project consisted of widening of a turn lane on SR 101 at Old Draketown Trail. Baldwin was responsible for grading, installing 18" Storm Drain pipe, drainage structures, GAB, milling asphalt, 18" Side Drain pipe (for driveways), paving asphalt. Our subcontractors were responsible for erosion control, striping, ground post mounted signs, and field fencing.

Intersection Improvements on SR 3 Conn. at Upper Riverdale Road

Upper Riverdale Road, Clayton County, GA 30274

This project consisted of widening Upper Riverdale Rd and improving the intersection with a new traffic signal and pedestrian pedestals. Baldwin was responsible for grading, 18" storm drain pipe, drainage structures, GAB, milling asphalt, and paving asphalt. Our subcontractors were responsible for erosoin control, traffic signals, guardrail, curb and gutter, sidewalk, concrete medians, striping and ground post mounted signs.

View Project

Intersection Improvements on SR 3 Conn. at Upper Riverdale Road

Upper Riverdale Road, Clayton County, GA 30274

This project consisted of widening Upper Riverdale Rd and improving the intersection with a new traffic signal and pedestrian pedestals. Baldwin was responsible for grading, 18" storm drain pipe, drainage structures, GAB, milling asphalt, and paving asphalt. Our subcontractors were responsible for erosoin control, traffic signals, guardrail, curb and gutter, sidewalk, concrete medians, striping and ground post mounted signs.

I-20 Ramp

600 Moreland Ave SE, Atlanta, GA 30316

Reconstruction and rehabilitation for operational improvements on I-20 at SR 42 Moreland Ave. We added over 7,700 SY of PCC Concrete and 965 LF of new Concrete Side Barrier on both On ramps and Off ramps on the project. This project also consist of adding 2 new traffic signals.

View Project

I-20 Ramp

600 Moreland Ave SE, Atlanta, GA 30316

Reconstruction and rehabilitation for operational improvements on I-20 at SR 42 Moreland Ave. We added over 7,700 SY of PCC Concrete and 965 LF of new Concrete Side Barrier on both On ramps and Off ramps on the project. This project also consist of adding 2 new traffic signals.

What Our Clients
Are Saying

Testimonials from the people and companies who count on Baldwin Paving to deliver quality work on time, every time.

Jason Garrett
Vice President of Land Development - Pulte Homes
Play Video